Title of the project
Increasing Energy Efficiency in Calarasi Rayon Hospital
General objective

Energy Efficiency in Calarasi Regional Hospital is improved

Term
06/2015 — 12/2016
Status
Finalized
Budget, €
335.0 K
The primary sector
Energy efficiency Energy efficiency
Type of assistance
Technical
Funding Partner
Federal Ministry for Economic Cooperation and Development (BMZ)
Locations
Călăraşi
Implementation Agency
German Development Cooperation through GIZ

• ~ 8.200 patients/year

• ~ 260 employees of Calarasi Hospital

• ~ 78.800 inhabitants of Calarasi Rayon

• Centre Regional Development Agency (RDA)

(Implementing Agency)

• Calarasi Rayon Council

• Calarasi Rayon Hospital

• Ministry of Regional Development and Construction

• Ministry of Health

Refurbishment measures of the refurbishment project

• Refurbishment of the boiler house by installing 2 new gas boilers (700 kW each)

• Installation of 504 m of pre-insulated pipes

• Installation of 1 heat substation for block 1 and block 2 (heating capacity 1,200 kW)

• Connection of the kitchen to the centralized hot water system (heat substation)

• Installation of a solar thermal system (around 100 kW)

Results

• Chapter on EE in public buildings of the Calarasi Rayon Socio-Economic Development Strategy is developed

• Study on increasing the energy efficiency of Calarasi Rayon Hospital developed

• EE Policy is approved by the Hospital and the Energy Management System is implemented

• Local Steering Committee is created and active (quarterly meetings)

+
-

Refurbishment measures of the refurbishment project

• Refurbishment of the boiler house by installing 2 new gas boilers (700 kW each)

• Installation of 504 m of pre-insulated pipes

• Installation of 1 heat substation for block 1 and block 2 (heating capacity 1,200 kW)

• Connection of the kitchen to the centralized hot water system (heat substation)

• Installation of a solar thermal system (around 100 kW)

Results

• Chapter on EE in public buildings of the Calarasi Rayon Socio-Economic Development Strategy is developed

• Study on increasing the energy efficiency of Calarasi Rayon Hospital developed

• EE Policy is approved by the Hospital and the Energy Management System is implemented

• Local Steering Committee is created and active (quarterly meetings)